The new factory in Narva was launched this autumn, signifying a milestone in the industrial development of the region. The factory extension project was kicked-off in 2015, when lack of space, capacity constraints and overload of new project implementations were foreseen.
Andrey Ponomarev at Fortaco Estonia was appointed as Project Manager. Working in this kind of project was familiar to Andrey, he has worked in similar start-up projects in the automotive industry. “But this was the biggest project, which I have participated from the idea and design stage. What is great, that our ideas and wishes have now been implemented in reality.”
For two years, before the construction work was started, Andrey participated the project documentation development, and paperwork took quite a long time to be finished. When a contract was signed, things started to be moving on fast. “The most memorable moments were, of course, in the beginning and at the end of construction. We built a good cooperation within our Fortaco team and with our external partners. The project was like a fresh wave for our daily routine jobs.”
Like in any project, there are always things you can learn from, and which need to be taken into consideration to make the next similar project easier. The biggest challenges were found during the construction work, mostly related to extra work, and to keep up with a somewhat tight schedule. In Fortaco team we had some parallel projects ongoing, the new equipment was needed to be purchased and installed to the right places at the same time when the new factory started to take a shape. “We had to investigate each task carefully, and also fast, to keep everything rolling. For example, when purchasing CNC machines and planning their foundation and installation, we had to make sure, these tasks would not influence on the construction schedule, and machines will be available for use when the permission of usage of the new building is received.”
There are some key elements Andrey would like to stress, when working with the project like this:
Carefully check the partners. The cheapest solution might not be the one with most benefits. Surprises during the construction process usually are not good, and you want to avoid them, as they have a habit to turn out to be expensive.
Check the commercial offer precisely, and make sure the contracts with all parties are transparent. Hereby you will avoid misunderstandings in case there happens to be any deviations from the contract or schedule during the process.
Be active – this is very important, time is money. All people involved must understand their role, and they also have to be willing to make decisions, if required. Some decisions need extra monitoring, but also this should be a rapid process.
Andrey was glad to see how the professional cooperation between the external partners and Fortaco team enabled the launch of new factory just according to the schedule, and he hopes Fortaco employees will be happy to work with the new equipment and technology. “I would like to say big thanks to all people who participated, including our partners and my colleagues in Fortaco. I believe, this new factory will create new opportunities to increase our business, and also employment in Narva region”.
21/11/2023
Fortaco Group invests in Steel Fabrication capacity
Cornerstone Ceremony in Gliwice, Poland 🧱 The cornerstone ceremony of our greenfield investment took place today in Knurow, Poland. With the…
10/11/2023
New factory in India
Fortaco and TATA AutoComp unveils cutting-edge cabin facility. Together we will provide safe and ergonomic vehicle cabins to the Indian and Asia…
31/10/2023
Transaction closed
Fortaco Group and Buisard Cabins have joined forces. Fortaco Group has acquired 100 percent of Buisard Cabins. A strategic alliance was established…
30/09/2023
Interim Review 1.1.-30.9.2023
Fortaco continued its consistent strategic path during the period under review. We completed the acquisition of MauserCABS as planned and acquired…